We have completed the first concrete pour on the Project. The basement floor slab was completed in a single continuous pour (263 cubic metres of concrete). Work was completed as planned and occurred without any incident.
We have completed the first concrete pour on the Project. The basement floor slab was completed in a single continuous pour (263 cubic metres of concrete). Work was completed as planned and occurred without any incident.