Alexion Turning Circle Project
Project Name
Alexion Turning Circle Project
Client:
Alexion
Location:
Monksland Ind Est, Athlone, Co Roscommon, N37 F586
Value:
€300K
Team:
- Design Team: PM Group
Sectors:
Pharmaceutical
Description
The Alexion Turning Circle project consisted of transforming the green area to the North of the Alexion campus into a car park and truck turning circle. The car park added 12 new parking spaces, 8 new E-charging spaces to the facility along with much needed truck turning space.
Key Packages
Groundworks, Water Main Diversion, Kerbing and Paving, Blacktop surface finish, Linemarking.
Key Deliverables
Accident and Incident Free
All excavations completed around known and unknown underground services
Project completed on time and to a high standard
All works were completed within a live facility and all transport and pedestrian access routes were maintained throughout the duration of the project.